WEBINAR TO BE HELD ON FRIDAY, MARCH 28 @ 10:00 AM EDT

Register here:

https://6ix.com/event/wallbridge-mining-corporate-update

TORONTO, March 27, 2025 (GLOBE NEWSWIRE) -- Wallbridge Mining Company Limited (TSX:WM, OTCQB:WLBMF) ("Wallbridge” or the "Company”) is pleased to report results from an updated positive Preliminary Economic Assessment ("PEA”) completed on its 100%-owned Fenelon gold project ("Fenelon” or the "Project”) located in the Abitibi Greenstone Belt, along the Detour-Fenelon Gold Trend, Quebec. A PEA prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101”) has been filed on SEDAR+ and is available on the Company's website and can be accessed here.

All results herein are reported in Canadian dollars unless otherwise indicated.

Get the latest news
delivered to your inbox
Sign up for The Manila Times newsletters
By signing up with an email address, I acknowledge that I have read and agree to the Terms of Service and Privacy Policy.

PEA HIGHLIGHTS

  • Average annual gold production of 107,000 oz per year over 16-year life of mine ("LOM”); 96% average gold recovery
  • Average annual gold production of 127,000 oz during the first five years
  • Average annual free cash flow of $120 million over LOM
  • After-tax Internal Rate of Return ("IRR”) of 21%
  • After-tax Net Present Value ("NPV”) of $706 million at base case gold price of US$2,200 and CAD$:US$ of 1.35:1.00 at a 5% discount rate
  • Initial capital expenditures (1) of $579 million
  • Sustaining capital expenditures (1) of $449 million
  • Total cash costs (1) of US$851/oz
  • All-in sustaining costs (1) ("AISC”) of US$1,046/oz
  • 16.6 Mt of mineralized material mined at an average grade of 3.34 g/t
  1. Non-IFRS financial measures with no standardized definition under IFRS. Refer to Non-IFRS Measures at end of this news release.
The Company cautions that the results of the PEA are preliminary in nature and include inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them to be classified as mineral reserves. There is no certainty that the results of the PEA will be realized.

Brian Penny, CEO of Wallbridge, commented:

"Fenelon is a gold project with tremendous potential. This updated Fenelon PEA generates strong project economics under a lower risk, higher grade, lower startup capital scenario. Fenelon has now reached another milestone with a robust PEA that demonstrates a viable path to development and attractive economic returns based on reasonable assumptions. The PEA was designed to be rigorous, using current cost data from contractors, suppliers and mining companies operating in the region to arrive at realistic projections. It represents a new starting point to build upon as we scope out the full opportunities at Fenelon and Martiniere, the two most advanced projects on our large, underexplored property. 

In this historically high gold price environment, we need to rapidly advance the project. The current plan has a shorter payback than the previous plan and allows us to consider expansion options after payback has been achieved.

I would like to thank everyone who contributed to the completion of this study, as well as our employees, stakeholders, and shareholders for their continuous support. I believe Wallbridge has a bright future, and we look forward to taking the necessary steps to increase value for our shareholders.”

Table 1: PEA Summary of Key Metrics and Project Economics

SUMMARY OF PROJECT ECONOMICS Mar 21, 2025
Base case gold price(US$)2,200
Exchange rate(CAD$:US$)1.35:1.00
Discount rate(%)5.0
NSR Royalty on Fenelon Mine Property(%)4.0
Mining Parameters
Average grade mined(g/t)3.34
Cut-off grades(g/t)2.25 (CTC)

2.51 (A51)

Mining rate(tpd)3,000
Total tonnage mined(Mt)16.6
Mine life(years)16.0
Processing Parameters
Processing recovery(%)96.0
Processing rate(tpd)3,000
Total tonnage milled(Mt)16.6
Average annual production(oz/year)107,000
Average annual production(first five years)(oz/year)127,000
Total production(oz)1,711,000
Capital Expenditures
Initial capital expenditure(3)($M)579
Sustaining capital expenditure(3)($M)449
Closure costs(3)($M)9
Salvage value($M)26
Operating Costs  
Total operating costs($/t milled)106
Cost Per Ounce
LOM total cash costs(1) (3)(US$/oz)851
LOM all-in sustaining costs(2) (3)(US$/oz)1,046
Financial Analysis
Pre-tax NPV5%($M)1,176
Pre-tax IRR(%)27
Post-tax NPV5%($M)706
Post-tax IRR(%)21
Post-tax payback period (from start of commercial production)(years)4.0
Profitability Index (post-tax NPV5%/initial capital)-1.22
  1. Total cash costs per ounce are operating costs, composed of mining (UG and OP), processing, water treatment and tailings, minesite G&A and royalty costs, divided by payable gold ounces.
  2. AISC/oz includes operating costs, sustaining capital expenditures to support the on-going operations, and closure costs, divided by payable gold ounces.
  3. Non-IFRS financial measures with no standardized definition under IFRS. Refer to note at end of this news release.
Financial Analysis

The PEA assumes a base case gold price of US$2,200/oz. Using that base case assumption, the Project generates an after-tax NPV of $706 million using a 5% discount rate and an after-tax IRR of 21%.

The Project generates cumulative free cash flow of $1,367 million and averages annual free cash flow of $120 million over a mine life of 16 years (Figure 1). Total taxes payable over LOM at the base case gold price is $776 million.

Figure 1. Annual After-Tax Free Cash Flow (millions)

Annual After-Tax Free Cash Flow (millions)

Sensitivities

The PEA financial economic analysis is significantly influenced by gold prices. At a gold price of US$3,000/oz and FX of CAD$:US$ of 1.35:1.00, the Project generates an after-tax NPV of $1,381 million and an after-tax IRR of 34% with a payback period of 2.4 years from the start of commencement of production (Table 2).

Table 2: PEA Sensitivity Analysis Gold Price

Gold Price

(USD)

FXNPV ($M)IRRPayback (Years)
1800 (-18%)1.3535313%5.7
1900 (-14%)1.3544315%5.0
2000 (-9%)1.3553217%4.6
2100 (-5%)1.3561919%4.3
22001.3570621%4.0
2300 (+5%)1.3579222%3.7
2400 (+9%)1.3587824%3.4
2500 (+14%)1.3596326%3.1
2600 (+18%)1.35104727%2.9
3000 (+36%)1.35138134%2.4
 

Operating CostsNPV ($M)IRR
Base Case -30%91225%
Base Case -20%84524%
Base Case -10%77622%
Base Case 0%70621%
Base Case +10%63519%
Base Case +20%56318%
Base Case +30%49016%
 

Capital Expenditures NPV ($M)IRR
Base Case -30%85530%
Base Case -20%80626%
Base Case -10%75623%
Base Case 0%70621%
Base Case +10%65519%
Base Case +20%60417%
Base Case +30%55215%
 

Production

Annual production over LOM is expected to average 107,000 ounces with peak production of 141,000 ounces in year 1 (Figure 2).

Figure 2. Production Profile

Production Profile

Capital Expenditures

The initial capital expenditures are estimated at $579 million, and the sustaining capital expenditures are estimated at $449 million (Tables 3 & 4). A contingency of $57 million and $20 million is included in initial and sustaining capital expenditures, respectively.

Initial and sustaining capital expenditures were estimated based on current costs received from vendors as well as developed from first principles, while some were estimated based on factored references and experience from similar operating projects.

Table 3: Initial Capital Expenditures

Cost ElementInitial Capital ($M)1,2
Mill217
Paste Plant43
Tailings and Water Treatment22
Capitalized Operating (Pre-production)75
Surface Civil & Infrastructure80
Mining Equipment31
Underground Development54
Underground Infrastructure28
Hydro Electric Line & Distribution29
Total Initial Capital$579
  1. All values stated are undiscounted. No depreciation of costs was applied.
  2. Non-IFRS financial measures with no standardized definition under IFRS. Refer to Non-IFRS Measures at end of this news release.
Table 4: Sustaining Capital Expenditures

Cost ElementSustaining Capital ($M)1,2,3
Mining Equipment145
Development161
Tailings & Water Treatment64
Paste Distribution Network8
Underground Infrastructure32
Surface Infrastructure29
Closure9
Open pit (OB Excavation + Contractor)3
Total Sustaining Capital$449
  1. All values stated are undiscounted. No depreciation of costs was applied.
  2. Non-IFRS financial measures with no standardized definition under IFRS. Refer to Non-IFRS Measures at end of this news release.
  3. Due to rounding, columns may not add up.
Total Cash Costs

The total unit cash costs are estimated at US$851/oz. The AISC is estimated at US$1,046/oz. Operating cost estimates were developed using first principles methodology, vendor quotes, and productivities being derived from benchmarking and industry practices.

Table 5: Total Cash Costs

 LOM Total

$ million

Average LOM

($/tonne milled)

Average LOM

(US$/oz)

Mining (UG & OP)90056390
Processing42325183
Water Treatment & Tailings66428
General & Admin.37422162
Royalty (4%)2021288
Total Cash Costs 2,31,965119851
  1. All values stated are undiscounted. No depreciation of costs has been applied.
  2. Non-IFRS financial performance measures with no standardized definition under IFRS. Refer to Non-IFRS Measures at the end of this news release.
  3. Total cash costs include mining (UG and OP), processing, water treatment and tailings, minesite G&A and royalty costs.

Mineral Resource Estimate

The updated mineral resource estimates ("MRE”) for the Fenelon and Martiniere deposits presented in this news release were prepared by Mauro Bassotti, P.Geo., an independent mineral resource consultant using all available information. The effective date of the 2025 MRE is March 20, 2025. The databases supporting the 2025 MREs are complete, valid and up to date, with close-out dates of October 22, 2024 and January 8, 2025 for Fenelon and Martiniere respectively. The 2025 Mineral Resource Statement for the Detour-Fenelon Gold Trend Property is presented below in Table 6. The statement provides the consolidated estimates for the Fenelon and Martiniere deposits. Details are provided in Item 14 of the PEA technical report.

Table 6: Detour-Fenelon Gold Trend Property 2025 Mineral Resource Statement by Deposit

DEPOSIT INDICATED INFERRED
Tonnes

(000's)

Gold

Grade

(Au g/t)

Gold Ounces

(000's)

()[\]\\.,;:\s@\"]+)*)|(\".+\"))@((\[[0-9]{1,3}\.[0-9]{1,3}\.[0-9]{1,3}\.[0-9]{1,3}\])|(([a-zA-Z\-0-9]+\.)+[a-zA-Z]{2,}))$/;return b.test(a)}$(document).ready(function(){if(performance.navigation.type==2){location.reload(true)}$("iframe[data-lazy-src]").each(function(b){$(this).attr("src",$(this).attr("data-lazy-src"))});if($(".owl-article-body-images").length){$(".owl-article-body-images").owlCarousel({items:1,loop:true,center:false,dots:false,autoPlay:true,mouseDrag:false,touchDrag:false,pullDrag:false,nav:true})}var a=$("#display_full_text").val();if(a==0){$.ajax({url:"/ajax/set-article-cookie",type:"POST",data:{cmsArticleId:$("#cms_article_id").val()},dataType:"json",success:function(b){},error:function(b,d,c){}})}$(".read-full-article").on("click",function(d){d.preventDefault();var b=$(this).attr("data-cmsArticleId");var c=$(this).attr("data-productId");var f=$(this).attr("data-href");dataLayer.push({event:"paywall_click",paywall_name:"the_manila_times_premium",paywall_id:"paywall_article_"+b});$.ajax({url:"/ajax/set-article-cookie",type:"POST",data:{cmsArticleId:b,productId:c},dataType:"json",success:function(e){window.location.href=$("#BASE_URL").val()+f},error:function(e,h,g){}})});$(".article-embedded-newsletter-form .close-btn").on("click",function(){$(".article-embedded-newsletter-form").fadeOut(1000)})});$(document).on("click",".article-embedded-newsletter-form .newsletter-button",function(){var b=$(".article-embedded-newsletter-form .newsletter_email").val();var d=$("#ga_user_id").val();var c=$("#ga_user_yob").val();var a=$("#ga_user_gender").val();var e=$("#ga_user_country").val();if(validateEmail(b)){$.ajax({url:"/ajax/sendynewsletter",type:"POST",data:{email:b},success:function(f){$(".article-embedded-newsletter-form .nf-message").html(f);$(".article-embedded-newsletter-form .nf-message").addClass("show");setTimeout(function(){$(".article-embedded-newsletter-form .nf-message").removeClass("show");$(".article-embedded-newsletter-form .nf-message").html("")},6000);dataLayer.push({event:"newsletter_sub",user_id:d,product_name:"newsletter",gender:a,yob:c,country:e})},error:function(f,h,g){}})}else{$(".article-embedded-newsletter-form .nf-message").html("Please enter a valid email address.");$(".article-embedded-newsletter-form .nf-message").addClass("show");setTimeout(function(){$(".article-embedded-newsletter-form .nf-message").removeClass("show");$(".article-embedded-newsletter-form .nf-message").html("")},6000)}});$(document).on("click",".article-embedded-newsletter-form .nf-message",function(){$(this).removeClass("show");$(this).html("")});