Updated Integrated Development Plan ("IDP”) Highlights (effective date January 1, 2024):

  • The DFS Case evaluates the Stage 3 Expansion to 1.2 million tonnes per annum ("mtpa”), consistent with the 2022 IDP, representing a 100% throughput increase from the 600,000 tpa Stage 2A Expansion design throughput (upgraded from 500,000 tpa in the 2022 IDP). Stage 3 involves a new standalone 1.2 mtpa process plant and supporting infrastructure, which is currently under construction, with mining focused on the Kora Central Zone within the Kora Deposit and Judd Deposit, utilizing a cut-off grade of 3.5 grams per tonne ("g/t”) gold equivalent ("AuEq”).

    • After-tax NPV5% US$680 million at US$1,900 per ounce gold and at around current spot prices, at US$2,600 per ounce gold, After-tax NPV5% is US$1.2 billion.
    • Average annual run-rate production of 303,288 ounces AuEq per annum, run-rate achieved in 2027 and a peak annual production of 319,360 ounces AuEq in 2027.
    • Life of Mine average cash costs of US$380 per gold ounce or US$694 per AuEq ounce and all-in sustaining cost ("AISC”)(2) of US$665 per gold ounce or US$920 per AuEq ounce over a 7-year mine life. The mine life is now extended to 2030, previously 2028 in the 2022 IDP.
    • Growth capital cost of US$194 million and life-of-mine sustaining capital cost of US$337 million.

      Get the latest news
      delivered to your inbox
      Sign up for The Manila Times newsletters
      By signing up with an email address, I acknowledge that I have read and agree to the Terms of Service and Privacy Policy.

  • The alternate PEA Case evaluates two-stages of expansions to a run-rate throughput of 1.8 mtpa, representing a 200% throughput increase from the 600,000 tpa Stage 2A Expansion design throughput (upgraded from 500,000 tpa). The ultimate run-rate throughput of the second expansion is referred to as Kainantu Stage 4 Expansion, operating two standalone process plants, larger surface infrastructure and mining throughputs achieved by mining Kora Upper, Lower, and Central Zones within the Kora Deposit, and the Judd Deposit, utilizing a cut-off grade of 4.0 g/t AuEq.

    • After-tax NPV5% of US$2.3 billion at US$1,900 per ounce gold and at around current spot prices, at US$2,600 per ounce gold, After-tax NPV5% is US$3.5 billion.
    • Average annual run-rate production of 413,593 ounces AuEq per annum, run-rate achieved in 2028 and a peak annual production of 484,692 ounces AuEq in 2034.
    • Life of Mine average cash costs of US$174 per gold ounce or US$633 per AuEq ounce and all-in sustaining cost ("AISC”)(2) of US$432 per gold ounce or US$822 per AuEq ounce over a 14-year mine life. The mine life is now extended to 2037, previously 2032 in the 2022 IDP.
    • Growth capital cost of US$201 million and life of mine sustaining capital cost of US$900 million.

  • Prior to the January 1, 2024 Updated IDP effective date, $15 million of expansion growth capital was spent. The total growth capital for the project, remains closely aligned with the operational guidance announced on February 22, 2024 of US$210 million. As at September 30, 2024, approximately 63% of the total growth capital for the Stage 3 and 4 Expansions is either spent or committed, and subsequent to quarter end, following the award of the river crossing construction contract in October, approximately 68% of total growth capital has either been spent or committed.

  • A major driver for the improvement in economics is the significant increase to the Mineral Resource estimate at Kora and Judd reported in Q4 2023 and incorporated into the Updated IDP, with Measured and Indicated Resources increasing by 14% to 2.6 million ounces at 10.0 g/t AuEq and Inferred Resources increasing by 73% to 4.5 million ounces at 8.5 g/t AuEq.

  • Both the DFS and PEA Cases are fully funded from existing cash balances, mine cash flow and available liquidity through credit facilities. K92 is in a strong financial position having, as at June 30, 2024, a cash balance of US$71 million and up to US$110 million in remaining undrawn liquidity from the Trafigura Credit Facilities. K92 recently announced record Q3 2024 AuEq production of 44,304 oz which has resulted in an increase to its cash balance, even with significant capital expenditures for the expansion (see October 9, 2024 press release).

  • Both the DFS and PEA Cases have a low environmental impact, being supplied with clean hydroelectricity, mining high grades outlining a low footprint, no-cyanide operation, and a majority of tailings reporting underground as pastefill.   K92 plans to upgrade the grid infrastructure, which is expected to significantly reduce greenhouse gas emission intensity per ounce produced near-term.

  1. AuEq - calculated on the following metal prices: Au - US$1,900/oz, Ag - US$25.00/oz, Cu - US$4.50/lb. Note that gold equivalent factors for the production estimates are different to those used for reporting the Mineral Resource estimate.

  2. AISC - All-In Sustaining Costs include cash costs plus estimated corporate general and administrative ("G&A”) costs, sustaining costs and accretion.
VANCOUVER, British Columbia, Oct. 16, 2024 (GLOBE NEWSWIRE) -- K92 Mining Inc. ("K92” or the "Company”) (TSX: KNT; OTCQX: KNTNF) is pleased to announce the results of its Updated Integrated Development Plan ("Updated IDP”) for its Kainantu Gold Mine Project (the "Kainantu Project”) in Papua New Guinea. The Updated IDP comprises two scenarios: 1) Kainantu Stage 3 Expansion Definitive Feasibility Study Case ("DFS” or "DFS Case”); and 2) Kainantu Stage 4 Expansion Preliminary Economic Assessment Case ("PEA” or "PEA Case”). The results of the Updated IDP will be set forth in an independent technical report prepared in accordance with National Instrument 43-101 - Standards for Disclosure of Mineral Projects ("NI 43-101”) within forty-five days from now.

The Updated IDP supersedes the January 1, 2022 effective date Integrated Development Plan ("2022 IDP”) and has delivered a significant improvement in economics in both the DFS Case and the PEA Case, and particularly the PEA Case, driven by the following key changes:

  • A significant increase to the Mineral Resource estimate at Kora and Judd reported in Q4 2023 (see December 5, 2023 press release), with Measured and Indicated Resources increasing by 14% to 2.6 million ounces at 10.0 g/t AuEq and Inferred Resources increasing by 73% to 4.5 million ounces at 8.5 g/t AuEq. This has extended the mine life for the DFS Case to 2030 from 2028 and the PEA Case to 2037 from 2032 from the 2022 Integrated Development Plan (see September 12, 2022 press release).
  • The new off-take agreement with Trafigura, commencing January 1, 2026, which has improved metals' payabilities for deliveries of concentrates, in addition to amending penalties, treatment and refining charges, and transport charges, all of which are better than the assumptions used in the 2022 IDP.
  • Significant margin expansion forecasted, as cash costs and all-in sustaining costs in the Updated IDP have only moderately increased from the 2022 IDP, while the economic evaluation gold price has increased from $1,600/oz to $1,900/oz to be closer aligned to recent peer studies and the current commodity price environment. Cut-off grades were slightly modified in the Updated IDP to achieve the optimal mine plan, with the cut-off grade for the PEA Case reduced from 4.5 g/t AuEq in the 2022 IDP to 4.0 g/t AuEq and the cut-off grade for the DFS Case increasing from 3.0 g/t AuEq in the 2022 IDP to 3.5 g/t AuEq. The updated IDP has made only limited changes to the mining method and recovery method from the 2022 IDP, with changes made to improve the pastefill plant and delivery design.
  • Limited forecasted Updated IDP growth capital cost inflation in a rising commodity price environment. This has been demonstrated to date from the construction activities well underway at the Kainantu Gold Mine for the Stage 3 and 4 Expansions. Importantly, the total growth capital for the project, remains closely aligned with the Operational Guidance announced in February 2024 of $210 million (see February 22, 2024 press release), that incorporated design and scope changes, including improving the expandability of the process plant and redesigning the pastefill plant to mitigate transport and delivery risk (trucking filter cake to an underground pastefill plant - previously involved extensive pumping and piping). Prior to the January 1, 2024 Updated IDP effective date, $15 million of expansion growth capital was spent. As at September 30, 2024, approximately 63% of the total growth capital for the Stage 3 and 4 Expansions has either been spent or committed, and subsequent to quarter end, following the award of the river crossing construction contract in October, approximately 68% of total growth capital is either spent or committed.
  • Throughput increase for the PEA Case to 1.8 mtpa from 1.7 mtpa driven by the Stage 2A Plant design throughput being upgraded from 500,000 tpa to 600,000 tpa as demonstrated from recent planted performance.

The Updated IDP, which includes the Kainantu Stage 3 Expansion DFS Case and the alternative Kainantu Stage 4 Expansion PEA Case, was independently prepared by Entech Pty Ltd of Perth, Australia ("Entech”); ATC Williams Pty Ltd ("ATC Williams”) of Brisbane, Australia; WSP Canada Inc. ("WSP”) of Ontario, Canada; Metallurgical Management Services Pty Ltd ("MMS”) of Perth, Australia, EMM Consulting Pty Ltd ("EMM”) of Queensland, Australia, H & S Consultants Pty. Ltd ("H&SC”) of Sydney, Australia, and; GR Engineering Services Limited ("GR”) of Brisbane, Australia, with some cost information provided by K92.

The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Mineral Reserves are defined by the Definitive Feasibility Study and are not predicated on the Preliminary Economic Assessment in any way.

John Lewins, K92 Chief Executive Officer and Director, stated, "The Updated Integrated Development Plan is a major milestone for K92, marking a significant improvement to mine economics by incorporating a larger updated Mineral Resource estimate, a new off-take agreement with Trafigura, more robust engineering designs and information from our ongoing construction activities, along with margin expansion from improved commodity prices.

This has resulted in the DFS Case NPV5% increasing from US$586 million at $1,600/oz in the 2022 IDP to, in the Updated IDP, US$680 million at $1,900/oz, or US$1.2 billion at near-spot prices of $2,600/oz. The PEA Case saw its NPV5% rise from US$1.3 billion at $1,600/oz in the 2022 IDP to, in the Updated IDP, US$2.3 billion at $1,900/oz or US$3.5 billion at near-spot prices of $2,600/oz gold.

Importantly, the realization of strong cash flow and the economic benefits of the Updated IDP are expected near-term. In less than nine months, the commissioning of the Stage 3 Plant Expansion is planned to begin, marking the start of K92's transformation into a Tier 1 Mid-Tier Producer. Concurrent with advancing the Stage 3 and 4 Expansions, we remain very active in improving upon the outcomes of the study, particularly through exploration. There are currently 11 drill rigs on site of which 6 are operating underground and 5 on the surface, focused on upgrading and expanding resources both near-mine and across our highly prospective gold-copper district.

Later this month, we are excited to host a large group of analysts and investors on-site to showcase our progress to date in multiple areas and also the mining-friendly jurisdiction of Papua New Guinea.”

1 - Kainantu Updated IDP - Definitive Feasibility Study Case

1.1 - DFS Overview

The DFS evaluates an expansion of mining and processing to a run-rate throughput of 1.2 mtpa, representing a 100% increase from the Stage 2A Expansion run-rate of 600,000 tpa. This expansion is referred to as the Stage 3 Expansion and involves on-site treatment of ore by a new standalone 1.2 mtpa process plant, utilizing single stage crushing, SAG and ball milling, along with gravity and flotation recovery.

The DFS and Mineral Reserve statement is derived from the global Kora and Judd Mineral Resource Estimate (September 12, 2023 effective date), net of post-resource mining depletion from September 12, 2023 to December 31, 2023, and does not incorporate post-resource-estimate drilling results.

Table 1.1: DFS Highlights

US Dollars unless otherwise stated

Updated IDP
Life of Mine

(starting January 2024)

Stage 3 Run-Rate(1)

(2027-2029)

Production  
Mine life (years)7 years 
Total mill feed (000s tonnes)6,1763,600
Average mill throughput (000s tonnes per annum)8821,200
   
Total Metal Production  
AuEq (000s ounces)1,561910
Gold (000s ounces)1,223666
Copper (million lbs)12692
Silver (000s ounces)2,9101,986
   
Peak Annual Production  
Year2027 
AuEq (000s ounces per annum)319 
   
Average Annual Metal Production  
AuEq (000s ounces per annum)223303
Gold (000s ounces per annum)175222
Copper (mlbs per annum)1831
Silver (000s ounces per annum)416662
   
Average Grade  
AuEq grade (g/t)8.5 g/t 
Gold grade (g/t)6.7 g/t 
Copper grade (%)1.0% 
Silver grade (g/t)19 g/t 
   
Average Recovery  
Gold recovery (%)93% 
Copper recovery (%)94% 
Silver recovery (%)78% 
   
Costs  
Mining cost (US$/t ore mined)$68.05$57.73
Processing cost (US$/t processed)$19.44$18.12
G&A cost (US$/t processed)$37.11$33.38
Paste plant cost ($/t processed)$10.31$13.32
TSF cost ($/t processed)$0.64$0.48
Transport and Insurance cost ($/t processed)$9.85$10.93
Total operating cost per tonne processed (US$/t)$145.40$134.56
Royalties ($/t processed)$10.90$10.93
Sustaining capital per tonne processed (US$/t)$54.59$34.47
Total cost per tonne processed (US$/t)$210.88$179.96
   
Growth capital expenditure ($m)$194 
Sustaining capital expenditure ($m)$337 
Total capital expenditure with closure costs ($m)$541 
   
Cash cost per ounce AuEq ($/oz)(2)

$694

$646

All-in sustaining cost per ounce AuEq ($/oz)(3)$920$789
Cash cost per ounce gold ($/oz)(2)$380$204
All-in sustaining cost per ounce gold ($/oz)(3)$665$397
   
Base Case Economic Analysis at US$1,900/oz Gold, US$4.50/lb Copper and US$25.00/oz Silver
After-tax NPV0%$869 million 
After-tax NPV5%(4)$680 million 
   
Economic Analysis at $2,500/oz Gold, US$4.50/lb Copper and US$25.00/oz Silver
After-tax NPV0%$1,359 million 
After-tax NPV5%(4)$1,091 million 
 
  1. Run-rate is calculated based on 2027-2029.
  2. Cash costs are net of by-product credits and are inclusive of mining costs, processing costs, site G&A and refining charges and royalties.
  3. AISC includes cash costs plus estimated corporate general and administration costs, sustaining costs, and accretion.
  4. Net present value is calculated utilizing monthly discounting.
1.2 - Kainantu Mineral Reserve Statement

The Mineral Reserve estimate outlined in the DFS was prepared by Daniel Donald FAusIMM MSME of Entech, in accordance with the classification criteria set out in the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves prepared by the CIM Standing Committee on Reserve Definitions. Daniel Donald is an independent consultant of the Company and is a Qualified Persons as defined by NI 43-101. The total Mineral Reserve for the Kainantu Project is shown in Table 1.2. The Mineral Reserve estimate is based on the Global Kora and Judd Mineral Resource estimate (September 12, 2023 effective date - refer to Table 1.3), net of post-resource mining depletion from September 12, 2023 to December 31, 2023, of 183,768 tonnes at 8.1 g/t Au, 0.9 % Cu and 15 g/t Ag.

Table 1.2 - Kainantu Mineral Reserve Statement (Effective Date January 1, 2024)

Kora and Judd Deposit Reserve Summary (January/2024)
          
 TonnesGoldSilverCopperGold Equivalent
 mtg/tmozg/tmoz%ktg/tmoz
          
Kora Deposit         
Proven2.957.40.70191.91.1319.40.89
Probable2.525.70.46191.61.0267.60.61
Proven & Probable5.476.61.16193.41.1578.61.50
          
Judd Deposit         
Proven0.248.30.06170.10.619.40.07
Probable0.476.50.10130.20.527.50.11
Proven & Probable0.717.10.16140.30.548.10.18
          
Consolidated         
Total Proven3.197.50.77192.01.0339.40.96
Total Probable2.995.80.56181.81.0287.60.73
Total Proven & Probable6.186.71.32193.71.0 setTimeout(function () { dataLayer.push({ 'event': 'article_complete', 'page_type': 'article', 'headline': 'K92 Mining Announces Significant Improvement to Economics With Updated Kainantu Gold Mine Integrated Development Plan ', 'article_id': '332124', 'content_category': 'TMT Newswire', 'content_subcategory': 'GlobeNewswire', 'article_type': 'free', 'author_id': '0', 'author_name': '', 'publish_date': '2024-10-17', 'publish_time': '05:25', 'feature_type': '', 'article_tags': '' }); },6000)