Kiniero on Track for First Gold in Q4 2025

Highlights:

  • First gold pour is on track for Q4 2025, key long lead items procured
  • Project Development team appointed, led by Chief Development Officer Dimitrios Felekis
  • Engineering for doubling plant capacity to 6Mtpa was awarded to Primero Engineering and is currently 24% complete
  • Additional Ball Mill awarded and scheduled for shipment in May 2025, SAG Mill on track for Q1 2025
  • Power station awarded with delivery from May 2025
  • Tailings Storage Facility (TSF) expanded design commenced with Knight Piésold
  • Civils contracts awarded, and concrete work has recommenced on site
  • Earthworks Fleet for TSF and infrastructure arrived in Guinea
  • Electrical and instrumentation awarded to ECG Engineering
  • Inferred resource drilling program for Mansounia nearing completion with more than 32,000 metres of RC and more than 2,600 meters of DD completed
  • Updated Feasibility Study for Kiniero on track for Q1 2025, led by AMC.